Concrete work began earlier this month for the Raise the Roof project.
- Concrete was poured above the upper seats (see photo with rebar) to establish the foundation for the press boxes and viewing rooms.
- Concrete was also poured below the upper seating area to help relieve the cramped seating in that section of seats. A row of seats was removed in the upper seating section, which allowed other rows to be moved to create more legroom and comfort.
Our goal is to complete Phase 2 of the Raise the Roof project by having the roof in place for the start of football season. Next steps are:
- Do a final pour of concrete and do masonry work in the back of the stadium to complete the support structure of the roof.
- We expect the roof contractor to begin installation of the roof in late July or early August. Installation should take 10 to 14 days.
Phase 3 includes the addition of an ADA compliant walkway from the Waterfall Clinic parking lot which is located above the stadium to the stadium seats. Target date for Phase 3 is the summer of 2020.
We’d like to thank all of our donors for your generous contributions so far. We could not have come so far without you!