August 28 Roof Update – Here we go!!!

The Raise the Roof Committee had a meeting with Renco the roof company this week.  Here’s our tentative timeline for Raising the Roof.

  1. The masonry subcontractor will come in to do the cement block work which will take about a week to two (by mid September).
  2. During the next three to four weeks, the crane, steel, lumber and glu lam beams will be delivered to the stadium and the beams will be put in place.
  3.  The final portion of the installation will be the roof, which should take two weeks.  Thanks to all of our volunteers who primed and painted the 200 sheets of plywood!

That makes the total time frame 6 to 8 weeks.  

We will need some more painting help when the lumber and glu lam beams arrive.  We’ll let you know so you can be a proud Pirate when you look at the new roof and say “That’s my artwork!”

PS.  The season opener is against the Bulldogs on September 6, 7PM.  At North Bend.

We’ll need a few Pirate Painters in a few weeks.
This entry was posted in General. Bookmark the permalink.

One Response to August 28 Roof Update – Here we go!!!

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.