1. Electrical work in the viewing boxes has been completed. ( Casey Waterman) Electrical Specialty
2. IT work has been completed in the viewing boxes by District 9. ( Sean Wirebaugh )
3. Insulation will be installed by the MHS construction class in November. ( Jesse Ainsworth )
4. Drywall and texture work will be done in November. ( Mckenzie Freeman )
5. Joe Slack has completed the plans for the ADA walkway. ( HGE )
6. ADA plans have been given to Johnson Rock and Knife River for cost estimates. ( Kortney Johnson and Chris Peach )
7. Ken Tedder will help with viewing box tables and counters.
8. Trench work will be done by the MHS construction class.
9. Fiber Optic Cable and electric service will be brought from the Drama building to the south stadium.
Thanks to all of our Pirate donors and supporters listed above and all of you who have contributed over the past three years!!!