1. An OSAA Grant has been submitted by Nancy Tedder, Mary Paczesniak, Sue Nowlin and Keenan Holte
2. Insulation to be completed by the end of February in the viewing boxes
3. Don Erickson has completed sealing and painting the stadium concrete block
4. Drywall and texture work will start after the insulation work is completed
5. We have received a bid from Johnson Rock for grading work for the ADA walkway
6. Electricity and fiber optic cable work to be done we hope in March
7. Sam Scott continues to work on cabinets for the viewing boxes
8. Ken Tedder will start work on front counters and tables for the viewing boxes. That work will take place after viewing box insulation, drywall, texture, and accent wall work is completed
9. Madrone accent walls to be done after insulation, drywall and texture work is completed
10. John Gunther had two nice articles in the World Newspaper about the Ford Family Grant and Susick Stadium as Oregon’s best.
Thanks for all your work and support !!!!!!!